Outline service PO item amounts mismatch in the ECC and SRM

$
0
0

Hi Experts,

 

I need your help to resolve the issue which i am facing in SRM as well as in ECC system.

 

When the Outline PO is created in SRM, the users are able to add the service line as well as the limit line item in the same PO by manually. I just want to know will the system allow to add the service or limit lines in the same PO which has the Outline ?, as per standard system behavior will system allow to add direct service or material or limit lines in the Outline PO ?, please clarify on this point because in ECC the amounts of the service items are merging to Outline items. Please let me know if you need any more information.

 

The current version is ECC ERP 6.0 and SRM: EHP3, SP06