Hi Gurus,
I have created Master Recipe in ECC. For this 1st i created a work center. When i am CIFing master recipe in curto_create this is showing operation has no activity message. Even for phase this is showing " Phase 0040 (014): Operation has no activity"
I have done all the relevant setting in resource ( like scheduling tab formula, capacity n formula) in recipe control key etc every possible way i have already tried but its throwing this message only.
Also in master recipe when i am trying to schedule in ECC itself no scheduling result are shown. I mean scheduling not at all happening..
Guide me what i am missing..