Hi Renjith,
I can see the one major difference after activating the check box in config, which gives additional info for the users who complete Notification / order created from maintenance plan.
After activating the check box, when you complete notification / order, you have an option of entering Completion date for the maintenance plan, below is for your reference.
If it was not activated.
This is what it was given in the help of that field
With this indicator you can:
- Activate a separate completion for the maintenance plan for the completion of call object notification and order.
- Activate a dialog for the completion of notifications and orders using list processing.
- Activate additional functionality for completing the call objects notification and order using a BAdI. (Technically should be possible)
Regards
Terence